Seaside road to reopen after Brighton Half

Patrick Barlow
BBC News, South East
Eddie Mitchell A derelict hotel next to a road with barriers blocking off the road.Eddie Mitchell
The A259 in Brighton will partially reopen on Monday after it was forced to close last week

The A259 will reopen on Monday and will be ready in time for the Brighton Half Marathon, the council has said.

Grand Junction Road has been closed for six days after warnings that the Royal Albion Hotel was at risk of "catastrophic collapse" prompted safety concerns and traffic about the road.

A spokesperson for Brighton & Hove City Council said the southern part of the road would reopen on 3 March with a contraflow after demolition works at the end of this week.

Organisers of the Brighton Half Marathon also confirmed the event would go ahead on Sunday as planned after fears it would be affected.

'We are very unhappy'

Speaking to BBC Sussex, Brighton & Hove Council's transport lead Trevor Muten said the westbound carriageway of the A259 was expected to be handed back to the council by the weekend.

He added: "I'm satisfied the work taking place will mean the Brighton Half Marathon can go ahead as planned and that we can get the A259 open to traffic again early on Monday morning.

"We are very aware of the impact this is having. We are very unhappy with that."

Muten said an 80 tonne crane was being transported from Cambridge to Brighton and would arrive on Thursday.

The crane would then be used to take down any hazardous structure and scaffolding in the hotel.

He added that the rest of the road would be opened "as soon as possible" subject to work by Britannia Hotels and their contractors.

The closure of the A259 has caused traffic chaos in the city centre, with businesses and residents in despair about the situation.

One business said it had taken a delivery driver an hour to travel around 250 yards (228.6m).

The Royal Albion was partially destroyed after a fire broke out in the building, believed to have been caused by a discarded cigarette.

Brighton & Hove City Council previously said it had asked for additional signage to reduce traffic around the road closures.

Follow BBC Sussex on Facebook, on X, and on Instagram. Send your story ideas to [email protected] or WhatsApp us on 08081 002250.