Date announced for opening of new railway station

Northumberland County Council An aerial image of Newsham Station with a lift and passenger bridge in the foreground and a road bridge behind and a large carpark on the far side of the line.Northumberland County Council
Newsham Station had been expected to open when passenger services on the Ashington Line resumed in December 2024 but was delayed

A date has been announced for the opening of a railway station on a new line.

Newsham, on the Northumberland Line, had been expected to open when passenger services between Ashington and Newcastle resumed in December, but was delayed.

It will now open on Monday 17 March, with tickets on sale from 10 March.

Northumberland County Council leader Glen Sanderson said: "Everyone involved with this project should feel incredibly proud to see another station opening."

It was initially hoped the 18-mile (29km) line would open with six new stations, but only two, Ashington and Seaton Delaval, were completed when the line reopened to passengers, six decades on from the last such services in 1964.

Geograph/Chris Morgan In the foreground Newsham signal box stands next to a road. It is a rectangular brick building with white framed windows overlooking the line. Behind there is the new lifts and passenger footbridge at the new station Geograph/Chris Morgan
Newsham's south signal box was structurally unsound and had to be demolished

Speaking in 2024, line programme delivery director Neil Blagburn described Newsham as the "biggest and most complex site" on the line.

It included the construction of a £30m road bridge over the line, which opened in August 2024.

Its construction costs were estimated to be just more than £11m in 2021 before spiralling, with inflation blamed for the rise.

The station's original signal box was found to be structurally unsound and was also demolished.

Northumberland County Council A large modern road bridge sweeps over a new railway station with construction workers wearing orange hi-vis jackets and trousers working on the barriers. Under the bridge construction work with diggers continues Northumberland County Council
The construction of Newsham Station involved a new £30m road bridge

Northern, which operates the services, says about 50,000 passenger journeys were made on the line in the first month.

Sanderson said: "This very ambitious project has been needed for decades, and the opening of Newsham Station will give those passenger numbers a further boost."

Rail Minister Lord Peter Hendy said: "Tens of thousands of people have already benefited from the historic reopening of the Northumberland Line, and I'm pleased many more will do so when Newsham Station opens."

The remaining three stations on the Northumberland Line, at Bedlington, Blyth Bebside and Northumberland Park, are scheduled to open throughout 2025.

Follow BBC North East on X, Facebook, Nextdoor and Instagram.

Related internet links